Outlined below are the steps completed in the redevelopment process:

  • Pre-construction and condition surveys
  • Safety perimeter fencing installation including fencing panels designed to recognize the traditional territories of the lək ̓ ʷəŋən (Lekwungen) Peoples and to educate and inform the public about the cultural and historical significance of the area to Esquimalt and Songhees Nations
  • Site entrance was widened to support future construction activities and a safe pedestrian crossing from Laurel Point pathway to the south side of Belleville Street
  • Major utility disconnections
  • Demolition activity including removal of the previous Clipper wharf, previous Clipper terminal and previous US Customs and Border Protection office building
  • As is standard practice, cultural and archaeological monitors from local First Nations were on-site to ensure Indigenous cultural heritage was respected and protected. No new archaeological sites were found.
  • Equipment installed onsite and adjacent properties for monitoring vibration and noise levels